Extension of platforms for EMU suburban 15 car work in progress at Thane PF 1, 2 & 3 (CSMT end) and at Dombivali PF 1A, 1 & 2, such as- 1) Dismantling and Insertion of point 125W. 2) Connection of new 125W crossover with newly laid 150 Mtr plain track by slewing it by 4-5 mtr. 3) 7 OHE mast/portal dismantling, shifting all main cabling and creating space for track slewing and extension. 4) Loading of scrap & unloading of 13 mtr rails using 11 BRN rake. 5) Dismantling and insertion of crossover 148 A/B by shifting 60 mtr using hydra/JCB & poclain machine. 6) PCTM machine turnout & crossover tamping of Point 135B, 146A, 148A & 148B. 7) Space creation to shift turnout ladder of point 149 A/B and further space creation for platform extension.