Developers, can you optimize this factory assembly line? This challenge tests your ability to maximize throughput in a constrained sequential process - a common problem in both computing and manufacturing!

25,026 Aufrufe • vor 1 Jahr •via X (Twitter)

2 Kommentare

Profilbild von Google for Developers
Google for Developersvor 1 Jahr

Here's a hint:

Profilbild von Kasey Schlaudt
Kasey Schlaudtvor 1 Jahr

At 10 hours the number of parts completed by the machines would be A10 - B9 - C8 - D7 - E6 so 6 completed products would be possible. It would take 5 hours for the first product and then 1 hour for every product after. Is that right?