Gallows Corner update 👇 10/13 flyover sections installed. 50m crash barriers + new traffic islands. Wildflower planting underway. Micro-tunnelling prep for the new Essex & Suffolk Water water main. Completion is planned for Spring 2026, with the flyover reopening first. Stay updated with a monthly newsletter here: