Video yükleniyor...

Video Yüklenemedi

Ana Sayfaya Dön

$IREN 2GW Sweetwater hub has been conditionally included in ERCOT’s Batch Zero process covering 1.4GW at Sweetwater 1 and 600MW at Sweetwater 2. That brings another piece of IREN’s 5GW pipeline closer to data center deployment, with the first 300MW targeted for Q4 2027.

175,701 görüntüleme • 3 gün önce •via X (Twitter)

12 Yorum

Scalar Field (YC P25) profil fotoğrafı
Scalar Field (YC P25)3 gün önce

The 5GW pipeline sounds great, but power approval is what turns it into an asset. This moves $IREN’s first 300MW one step closer to real revenue.

Zeek | Insights 📊 profil fotoğrafı
Zeek | Insights 📊3 gün önce

I’m giving the credit to Fran’s he was on it a few days ago

Tonton profil fotoğrafı
Tonton3 gün önce

Additionnal capacity, not factorized in their already announced 5,5GW, will come soon alive in Texas !!!!

Tyler James profil fotoğrafı
Tyler James3 gün önce

The Sweetwater 1 substation was already energized earlier this year, so this is ERCOT catching up to what's already built. First 300MW is still Q4 2027.

LongBull profil fotoğrafı
LongBull3 gün önce

Nice one

𝐓𝐡𝐢𝐧𝐤𝐢𝐧𝐠 𝐀𝐛𝐨𝐮𝐭 𝐈𝐭 profil fotoğrafı
𝐓𝐡𝐢𝐧𝐤𝐢𝐧𝐠 𝐀𝐛𝐨𝐮𝐭 𝐈𝐭3 gün önce

Are all these conditional approvals published somewhere or do investors have to rely on individual corp announcements?

DDH profil fotoğrafı
DDH3 gün önce

This is HUGE for $IREN. 🚀 2GW conditionally included in ERCOT’s Batch Zero process is another major step toward turning IREN’s massive power pipeline into actual data center capacity. With the first 300MW targeted for Q4 2027, the path from power → compute → revenue is getting much clearer. The 5GW pipeline is starting to look very real. 🔥

Eric Everett profil fotoğrafı
Eric Everett3 gün önce

Its hilarious how all these AI bots are AI speaking about interconnects being what matters when the substation is already energized.

adrian profil fotoğrafı
adrian3 gün önce

@grok is this significant in any way?

Banana Republic profil fotoğrafı
Banana Republic3 gün önce

Conditional means $IREN still needs grid connection agreements signed before this counts as final. Real step forward, not a done deal yet... good to see them tracking the distinction.

Site Specs profil fotoğrafı
Site Specs3 gün önce

Base Load in that Batch Zero screen means ERCOT treats the campus as known demand. It doesn't put the whole hub on one performance bond. The first building is already going up, so folding Sweetwater 2 earthworks into that same bond overstates how long the surety is committed. Is the first hall going out as its own bid package?

Energy for AI profil fotoğrafı
Energy for AI3 gün önce

Getting Conditional Base Load classification in ERCOT Batch Zero could make these data centers significantly more bankable. We saw a similar outcome with Hut 8. I’ve written a short blog post on my timeline explaining what Base Load classification means, why it matters, and how it can impact the bankability of large data center projects.

Benzer Videolar

The next two months put $IREN's entire pivot on one milestone. Horizon 1, its first GB300 super cluster at Childress, is targeted to hand off to $MSFT in Q3, roughly July through September, the opening delivery under the five year, $9.7 billion Microsoft contract and the point where that contract starts turning into revenue. For a year the company has been buying the hard things. Power, land, financing. Now it has to turn them into delivered compute. That is the whole test. "The world is structurally short compute, and the bottleneck is delivered data center and GPU capacity," said Daniel Roberts, Co-Founder and Co-CEO of $IREN. Horizon 1 is him putting that to the proof. Capacity nobody can energize is worthless. Capacity handed to a hyperscaler on schedule is the business. The rest of the window fills in around it. The Mirantis acquisition, signed in May, is pending close and adds the software layer to run the fleet. $3.1 billion of ARR sits under contract against a $4.4 billion target, so there is room for another customer, and management is openly chasing one. The $3.65 billion GPU financing that closed June 1 already funds most of the $MSFT hardware, with $NVDA and $DELL on the supply side. Sweetwater 1, energized in May, keeps ramping power behind all of it. The full year FY2026 results that put real numbers on all of this land just past the window, late August into September. The catalysts here are operational first, reported second. What makes that timeline credible is the record behind it. $IREN hit 50 EH/s on the schedule it set, energized Sweetwater 1 on schedule, and has Horizon 1-4 tracking for year-end. This is a team that keeps turning secured power into online capacity on time, and each build makes the next one faster. How many names in this AI buildout are actually delivering capacity on schedule, not just announcing it? It's not a sprint, it's a marathon.

Patient Investor

105,170 görüntüleme • 2 ay önce

$IREN: Fake vs Real Power Something that appears to be overlooked by the broader $IREN investor community, and especially by analysts, is the recent set of ERCOT (Texas grid) changes. For a long time, most data center developers could purchase random parcels of land, or secure land through option agreements, and then claim they had a “multi-GW” power pipeline in Texas. Somewhere in the footnotes, they would then clarify: *Pending grid studies, interconnection agreements, and ERCOT approvals.* It used to be difficult to distinguish between what was “real” power and what was, at best, aspirational. That was especially true for projects already halfway through the process, such as those that had partially completed grid studies but had not yet secured the remaining approvals. This led to a tsunami of “fake” power claims from operators across the industry, many of whom used inflated pipeline claims to support their valuation and strengthen their negotiating position. With the new ERCOT changes in place, that is no longer possible. The statewide grid operator has now introduced a new batching system that categorizes projects based on real, tangible progress and the steps they have taken, queuing them accordingly. As of today, it largely comes down to whether your project is in “batch 0, base load”. If you are not in this initial batch, you can effectively kiss your project goodbye until, at the very earliest, 2028. For the first time, counterparties (i.e., customers) and investors alike can distinguish between what is real and what is fake, or at best still many years away. This plays directly into $IREN's hands, as it is one of the few operators in the space that has always been straightforward about its power pipeline, only announcing sites that have gone through all the necessary steps and approval requirements. As such, $IREN's Sweetwater 1 & 2 sites are all but guaranteed to be in the first “base” batch, with additional unannounced sites also likely to be part of it. These new changes undoubtedly strengthen $IREN's negotiating position, as the pool of seemingly near term capacity has now shrunk by a meaningful margin.

𝐀𝐠𝐫𝐢𝐩𝐩𝐚 𝐈𝐧𝐯𝐞𝐬𝐭𝐦𝐞𝐧𝐭𝐬

59,558 görüntüleme • 5 ay önce

$IREN BELOW $100 is STEAL !!! ✅ Chamath recently said that building 1 GW of AI data center capacity today can cost around $100 billion. Whether the number ends up being $80B, $100B, or somewhere in between isn’t the main takeaway. The takeaway is this: Power-ready AI infrastructure has become one of the most valuable assets on the planet. Now look at what IREN already controls: Sweetwater, Texas — 2.0 GW Childress, Texas — 750 MW Oklahoma — 1.6 GW South Australia — 800 MW Spain (Nostrum) — 490 MW Prince George, Mackenzie & Canal Flats — Existing AI cloud infrastructure Total portfolio: 5.8 GW of secured power capacity. What excites me most is what should be energized by 2026: ⚡ Sweetwater Phase 1 (~1.4 GW) ⚡ Childress (750 MW) ⚡ Prince George & Mackenzie continuing to scale AI cloud operations That’s already ~2.1+ GW of energized AI infrastructure either operating or coming online. Using Chamath’s framework: 2 GW = ~$200 billion of replacement value Yet IREN trades around a $18-20 billion market cap Even if Chamath is off by 50%, you’re still looking at a valuation gap that is hard to ignore. The market is pricing IREN like a miner. The bull case is that it’s becoming a large-scale AI infrastructure platform. By math alone, if ~2 GW is energized and available for AI workloads by 2026, a $100B+ market cap doesn’t seem crazy. That would imply a stock price potentially in the $150-$250 range, based solely on the value of the energized AI infrastructure—not even giving full credit to the remaining 3.7+ GW in the portfolio. 🤯🤯🤯 This is why I believe the market is dramatically underestimating what IREN is building. ✅ Gigawatts of power ✅ Strategic land positions ✅ Grid access ✅ Permits & approvals ✅ AI-ready infrastructure

investing

79,876 görüntüleme • 2 ay önce