Rasmale’ Land Reclamation Project Update Project execution at Site A has reached 51.64% completion, with 71 hectares reclaimed to date out of the planned 137.5 hectares. Reclamation operations are being undertaken using Cristóbal Colón, operated by Jan De Nul, in line with established engineering standards.