November 2025 Site Update | #PolarisForge1 Winter is here in full effect — and our teams continue driving this project forward with unmatched commitment. $APLD Building 1 (100 MW Critical IT Load) 🔹Both phases of RFS complete 🔹Data halls turned over to tenant 🔹IST completed Building 2 (150 MW Critical IT Load) 🔹Strong exterior + interior progress 🔹SOG pours underway 🔹First CAT generator set 🔹Sitework + U/G utilities pacing strong 🔹Winter roof enclosure entering fabrication Progress here isn’t seasonal — it’s the result of a team built to execute, even in North Dakota winter.
Applied Digital22,239 просмотров • 7 месяцев назад

September 2025 update from #PolarisForge1 ⚡ Building 1 (100 MW): Final commissioning underway — first 50 MW IT turnover in progress. 🏗️ Building 2 (150 MW): Underground MEP advancing as precast races to cover the footprint. Steady steps toward delivery. $APLD
Applied Digital14,765 просмотров • 9 месяцев назад