Replacing 196 bridge structures while keeping Metro-North service moving was no small task. But the Park Avenue Viaduct project was completed 60 months ahead of schedule and $195 million under its initial $960 million budget. This vital structure carries 98% of Metro-North trains and every train entering and leaving... show more