
Applied Digital
@APLDdigital • 11,034 subscribers
Applied Digital designs and operates high-performance AI data centers that turn power into progress. $APLD
Videos

Go inside the closed-loop cooling system designed for our AI infrastructure in Behind the Build Episode 4. The cooling liquid stays inside the system, circulates continuously and is reused again and again. The result is simple: our data centers use almost no water for cooling.
Applied Digital2,010,119 次观看 • 1 个月前

Long before a data center becomes operational, there are conversations that shape how a project moves forward. In Behind the Build | Episode 2: The Townhall, we take you inside a real community meeting in Harwood, North Dakota to show what those conversations actually look like.
Applied Digital1,933,408 次观看 • 2 个月前

Misconception: All AI data centers consume massive amounts of water for cooling. Reality: Applied Digital's don't. $APLD Episode 4 of Behind the Build takes you inside our closed-loop cooling system and the engineering behind it. See why in Episode 4 of Behind the Build:
Applied Digital12,005 次观看 • 1 个月前

November 2025 Site Update | #PolarisForge1 Winter is here in full effect — and our teams continue driving this project forward with unmatched commitment. $APLD Building 1 (100 MW Critical IT Load) 🔹Both phases of RFS complete 🔹Data halls turned over to tenant 🔹IST completed Building 2 (150 MW Critical IT Load) 🔹Strong exterior + interior progress 🔹SOG pours underway 🔹First CAT generator set 🔹Sitework + U/G utilities pacing strong 🔹Winter roof enclosure entering fabrication Progress here isn’t seasonal — it’s the result of a team built to execute, even in North Dakota winter.
Applied Digital22,239 次观看 • 9 个月前

May brought continued momentum across Polaris Forge 1 in Ellendale, North Dakota, as the campus moves closer to key operational milestones. $APLD ☀️ PF1-2 | 150 MW Critical IT Load: Customer move-in activities are underway, around-the-clock operations are set to begin in mid-June, and commissioning activities continue to advance toward key operational milestones. Polaris Forge 1-3 | 150 MW Critical IT Load: Construction remains on schedule and is tracking ahead of key milestones. Interior concrete slab work on the west side is nearing completion, and additional construction resources are expected to support the next phase of development. The work happening today is laying the foundation for the next generation of AI.💥
Applied Digital10,584 次观看 • 3 个月前

“If you build it, they will come.” Our CEO Wes Cummins shares how Applied Digital’s Field of Dreams strategy — building Polaris Forge 1 before a single customer — led to one of the world’s largest liquid-cooled #AI factories, now nearing initial energization. $APLD 🎧 Hear the story on Brew Markets: YouTube →
Applied Digital20,621 次观看 • 11 个月前

Stranded power. Free cooling. $50–$60M A year in savings. North Dakota isn’t a workaround—it’s the edge. Applied Digital is building AI Factories where the climate cuts costs, and the grid doesn’t flinch. 📄 White paper: $APLD #AITCO #AIFactories #AppliedDigital #DataCenters #NorthDakota #StrandedPower #FreeCooling
Applied Digital21,260 次观看 • 1 年前

This February, Polaris Forge 2 continues to execute to plan. $APLD Building 1 (150 MW Critical IT Load): Precast erection continues as MEP trades mobilize inside the facility to advance interior fitout efforts. Building 2 (150 MW Critical IT Load): Deep foundations will be complete by month end, with concrete foundations and underground MEP installation progressing in parallel. Precision. Speed. On schedule.
Applied Digital11,952 次观看 • 6 个月前

January sets the tone. Progress continues at Polaris Forge 1. $APLD POLARIS FORGE 1-2 (150 MW Critical IT Load) 🔷 Slab-on-grade complete on the east side; underground work advancing on the west 🔷 CAT generator installation nearing complete, with medium-voltage switchgear and GPS equipment now being installed. 🔷 West-side roofing nearing completion; main data hall piping complete across key gallery areas. POLARIS FORGE 1-3 (150 MW Critical IT Load) 🔷 Foundations and major underground infrastructure nearing completion 🔷 Precast erection underway, officially kicking off vertical construction. Each milestone reflects steady execution as Polaris Forge 1 continues to advance on schedule. #PolarisForge1 #EllendaleND #AIInfrastructure
Applied Digital13,151 次观看 • 7 个月前

“We've put all the pillars in place to actually go and execute this at scale, really rapidly.” — Wes Cummins, CEO on CNBC Those pillars: construction, supply chain, power, and capital. Now totaling 600 MW of contracted capacity, Applied Digital is scaling the next generation of AI factories. $APLD
Applied Digital15,356 次观看 • 10 个月前
没有更多内容可加载