Progress update from Polymatech’s Nava Raipur Semiconductor SEZ:
0:00 / 0:57

Progress update from Polymatech’s Nava Raipur Semiconductor SEZ:

Polymatech Electronics

@polymatech2129 位关注者

在 X 上查看
211 个赞下载原帖

1,138,569 次观看

Progress update from Polymatech’s Nava Raipur Semiconductor SEZ: • 11 kV power connection commissioned • Peripheral boundary wall completed • Initial ATMP facility established in a 5,000 sq. ft. double-jacketed building The facility will support power, humidity and environmental validation, allowing necessary adjustments to be made before the main manufacturing facility is completed. ATMP operations are scheduled to commence within 10 days, while construction of the main factory building will begin shortly. Steady, disciplined execution as Polymatech expands its global semiconductor manufacturing capabilities.